A practical guide for inflatable operators, hirers, event companies, parks, purchasers and resellers. Start with the application, identify the likely blower requirement, then assess running load, starting demand and energy cost.
The largest motor is not automatically the best choice. An inflatable needs sufficient airflow at the pressure required by its design. The correct blower should therefore be selected from the inflatable's actual requirements and the manufacturer's specifications.
Once the blower is selected, you need to understand its running current, starting current and the energy consumed over the operating period — especially when several blowers share a generator or restricted electrical supply.
Select the application that most closely matches your inflatable. The tool provides a starting-point recommendation from the Gibbons range. Final blower selection should always be confirmed against the inflatable manufacturer's required pressure, airflow and connection specification.
This is a planning tool, not a substitute for a blower performance test. Where your inflatable supplier specifies a required airflow or pressure, use those figures as the primary selection criteria.
Suitable starting point for smaller inflatables, subject to the inflatable manufacturer's pressure and airflow requirements.
View blower rangeTechnical note: volts × amps gives apparent power (VA/kVA), not exact real power (W/kW). The energy figures above are therefore estimates based on apparent load. For accurate commercial energy costing, use measured real power/kWh or manufacturer electrical-input data.
Inflatable size can be a useful indication of scale, but dimensions alone do not determine the correct blower. Different inflatables have different air requirements, operating pressures, construction, seams, valves and intended operating conditions.
If the inflatable manufacturer states a minimum airflow or operating pressure, those values should take priority over a generic size-based recommendation. A blower that produces high airflow at the wrong pressure may not be the best solution.
| Model | Motor | Airflow at 1.0 kPa | Running current | Starting current | Typical planning role |
|---|---|---|---|---|---|
| GX-900 | 1.0 hp | 900 m³/hr | 6.0 A | 11 A | Smaller inflatables |
| GX-1250 | 1.5 hp | 1,250 m³/hr | 10.5 A | 25 A | Medium / larger inflatables |
| GX-1650 | 2.0 hp | 1,650 m³/hr | 10.5 A | 25 A | Large inflatables |
For a precise energy calculation, use the blower's actual real-power input. A plug-in power meter suitable for the load can provide measured watts and accumulated kWh. This is preferable to estimating kW from amps alone.
If a blower uses 1.1 kW and runs for 8 hours, the simplified calculation is 1.1 × 8 = 8.8 kWh. At £0.30/kWh, that is £2.64.
If the same blower runs 50 days per year, the example becomes 8.8 × 50 = 440 kWh, or £132 at £0.30/kWh.
When an electric motor starts from stationary it must accelerate its rotating components to operating speed. The current drawn during this starting period can be substantially higher than the normal running current.
A GX-1250 has a listed running current of 10.5 A and starting current of approximately 25 A. The 25 A figure is a temporary starting demand, not a continuous 25 A consumption.
Three units have a combined listed running current of 31.5 A. If all three started simultaneously, their nominal starting currents could total approximately 75 A. Actual system behaviour depends on the supply, motor characteristics and protection equipment.
Sequential starting reduces the chance that several motors impose their temporary starting demand on the generator or electrical circuit at the same instant. It does not eliminate starting current.
For occasional use, check that the household circuit and socket are suitable for the blower. Estimate energy cost from measured or manufacturer-supplied real power and the time used.
Calculate annual energy consumption across the blower fleet. When comparing equipment, consider useful airflow and pressure alongside electrical input, reliability and operating hours.
Temporary supplies and generators must accommodate the continuous blower load plus starting demand and every other connected load, including lighting, sound, catering and refrigeration.
Consider generator continuous rating, motor-starting capability, power factor, transient response and the distribution equipment. Starting multiple blowers together can cause an avoidable peak.
Long daily operating hours and many continuously running blowers can make electricity a significant operating expense. Accurate metering is particularly valuable for forecasting and cost control.
Multiple large blowers may create substantial electrical demand. Distribution capacity, cable runs, voltage drop, protection and generator capacity all need consideration.
Generator selection is more than adding motor horsepower. Consider the total continuous electrical load, motor starting requirements, generator starting capability, power factor, other equipment and the electrical distribution system.
At 230 V and 31.5 A combined running current, the simplified apparent running load is approximately 7.25 kVA. The temporary starting demand can be much higher, which is why generator transient performance and sequential startup matter.
Generator sizing, temporary distribution, circuit protection, cable selection and voltage-drop calculations should be assessed by a suitably competent electrical professional and in accordance with applicable local requirements.
Airflow at a stated pressure, operating pressure capability and the blower's suitability for the inflatable should be compared.
Running current, starting current, voltage, real electrical input and compatibility with generators or site supplies should be checked.
Purchase price is only one part of the equation. Consider energy, maintenance, reliability, operating hours and expected service life.
Weight, handling, stacking, protection, environmental suitability, noise and connection arrangements can all affect the real-world value.
The correct blower is the one that provides the required airflow and pressure for the inflatable while fitting the available electrical infrastructure. Once that blower is selected, calculate the running load, understand the temporary starting demand and estimate the energy cost from actual or reliable electrical-input data.
For a single domestic inflatable this may be a simple calculation. For a hire fleet, public event or inflatable park, the same principles become essential for generator sizing, distribution planning and controlling operating costs.
Explore the Gibbons range and compare blower performance and electrical requirements for your application.
Electrical safety: This guide is for general information and planning. It is not a substitute for electrical design, risk assessment or professional electrical advice. Always use the latest manufacturer specifications and applicable local requirements when designing or operating electrical supplies, generators or temporary installations.